2017 Sidewalk Improvements

Project includes the construction of sidewalks, ramps, and driveways at various locations throughout the City.  The project is funded through a grant from the Federal Transit Authority (FTA).  Project went out to Bid in June 2017 and was awarded by the Commission at the July 24, 2017 meeting. 

Construction Company:  Artillery LLC
Original Contract: $683,350.00
Contract Days:

120 working days (August 10, 2017 – February 14, 2018)


Construction Status: Construction began in August 2017 and is approximately at 50% complete.  Sidewalk installation has begun on S. 29th Street & Colonel Plummer Drive.   

  • 6