2017 Sidewalk and Bus Shelter Improvements


Project includes the construction of Bus Pads at existing bus stops, sidewalks, ramps, and driveways at various locations throughout the City.  The project is funded through a grant from the Federal Transit Authority (FTA).  Project went out to Bid in March 2017 and was awarded by the Commission at the April 10, 2017 meeting.

Construction Company:  RDH, LLC.
Original Contract:
Current Contract:
$261,000.00
$304,040.00
Original Contract (Days):

139 working days (May 15, 2017 – Nov. 28, 2017)


Construction Status: Construction began in May 2017 and is 100% complete.  

  • 5