Project includes the final phases to complete the War Memorial and includes the Children’s and Ceremonies Plaza, and a parking lot.  The project was made possible through a grant from Texas Parks and Wildlife and matching funds from the City of McAllen.

Project Budget: $500,000 ($250,000.00 Grant; $137,500.00 Cash; $112,500.00 In-Kind)
Phase II: : Contract Awarded to Celso Gonzalez Construction $243,823.87 on November 13, 2017 by City Commission.  Construction scheduled to begin January 2018.
Phase III: Under Design.

Construction Status: Phase I is complete, with the driveway, parking lot, and striping as of late August 2017.  Phase 2 is anticipated to begin construction in January 2018.