Storage Building Addition

New construction of 2,500 Sq. Ft. one story structure for storage building  with metal R-panel veneer construction and metal R-panel roof on concrete slab, to match existing building. To including 1,425 Sq. Ft. Canopy attached to the structure.

Architectural Firm:               In-House by Engineering
Construction Company:     Celso Gonzalez Construction, LLC
Original Contract:                $177,340.00
Original Contract (Days):    45 - Calendar Days   (July . 24, 2018 - September 06, 2018)

 

Construction Status: As of July, 2018:  The project is 16 calendar days into construction.  The original contract provided for 45 Calendar days with an estimated completion date of September 06, 2018.  Crews are compacting the compacton soil and will be forming the foundation. 

 