Storage Building Addition

New construction of 2,500 Sq. Ft. one story structure for storage building  with metal R-panel veneer construction and metal R-panel roof on concrete slab, to match existing building. To including 1,425 Sq. Ft. Canopy attached to the structure.

Architectural Firm:               In-House by Engineering
Construction Company:     Celso Gonzalez Construction, LLC
Original Contract:                $177,340.00
Original Contract (Days):    45 - Calendar Days   (July . 24, 2018 - September 06, 2018)

 

Construction Status: As of August, 2018: 

The project is 77 calendar days into construction.  The construction crews have completed the placement of the foundation.  The contractor  has  started the erection of the metal building. The erection of the metal building will take maximum of three weeks.  Due to manufacture fabrication the project completion time is scheduled for October 31st

3

4