Bond Projects: Roadway Improvements

Bicentennial (Trenton to 107)

Project being designed by Halff Associates, Inc. Ninety-five percent (95%) plans are in development. A formal Public Hearing was held on May 3rd. Comments are being incorporated into final draft of environmental assessment. Preparation is underway for the traffic noise workshop. Preliminary utility coordination and relocation continues. Project letting is scheduled for March 2019.

  • 21
  • Tabulated Data

Dove (41st to Bentsen)
Design and utility coordination tasks continue. City funded project for FY 18-19. Finalizing survey for design.

  • 23
  • Tabulated Data

Kennedy (Ware to Bentsen)

Formerly Erie Road extension project. Design is being done in-house and is at 30%.    

  • 25
  • Tabulated Data

29th Street (Oxford to 107)

Project design by Dannenbaum Engineering.  Roadway design and ROW acquisition is complete. The project was awarded by City Commission on October 23, 2017 to 2GS, LLC.  Notice to proceed with construction was issued on January 19, 2018.

Construction Company:          2GS LLC
Current  Contract:                    $ 2,927,564.62
Contract Days:                          443 Working Days

Construction Status:   A total of 4,000 LF of storm sewer pipe has been installed and waterline construction has been completed. Pending are the remainder of the storm sewer, utility crossings and Phase III construction. Once final utility crossings are done the concrete work will be completed before paving improvements can commence. Chang order No. 4 was approved at the 11/12/18 City Commission meeting that included multiple utility crossings needed within the construction limits before paving can commence. Paving is scheduled to commence within the next two weeks. All items within the paving extents are being finalized.



5

Auburn (10th to Main)

ROW acquisition is complete.  Project is under design by Melden and Hunt as part of the Northpark Village Subdivision Development Agreement. The Developer is also responsible for the construction of the roadway.

  • Tabulated Data

OAKLAND

On hold, pending ROW acquisition.